Physical Progress as on October 31, 2019

 

Item Status (%)
C-I Dam 82.77
C-II HRT (Head Race Tunnel) 98.46
C-III Power House 73.60
E&M Works (Electro-mechanical) 77.61
Transmission 100.00
Others
TOTAL 85.13